WHO/Government of India Collaborative Programme

Guidelines for Preparation of Proposals Monitoring & Information on Technical Collaboration

 

WHO/Government of India Collaborative Programme

Guidelines for Preparation of Proposals Monitoring & Information on Technical Collaboration

 

*     Agreement for Performance of Work (APW)

An APW is a contract between WHO and the contracting party primarily for:

*      undertaking studies/surveys;

*      undertaking pilot projects;

*      developing manuals and training materials;

*      engaging experts for development of guidelines/preparation of documents/ publications of specified nature required for strengthening national health care capabilities without direct supervision of WHO;

*      undertaking monitoring, supervision and management of project.

Salient features and Guidelines for an APW

a)     APWs are normally concluded with institutions; however,in exceptional circumstances, APWs may be concluded with individuals.

b)     Proposals should be submitted as per the format in Annexure 2. All proposals up to an estimated budget of US$ 50,000 (INR 2,000,000 approx.) will be processed in WCO. Proposals for higher amounts will be referred to the WHO Regional Office.

c)      For printing the final report and product of the APW, it is permissible to keep an amount up to INR 20,000. This can be included in the proposal budget.

d)     The duration of the APW should be feasible taking into consideration the nature of the activity, time frame for delivery of any equipments/consumables required to carry out the activity, staff to be recruited and other similar factors but should not exceed one year.

e)     Long-term studies/projects (with duration exceeding one year) may be undertaken in a phased manner, i.e. initially APW for a maximum duration of one year may be issued. Subsequent phase(s) may commence upon completion of the previous phase under separate APW(s).

f)       The first instalment can be a maximum of 25% of the APW amount.

g)     The instalment schedule of an APW is result-oriented and based on delivery principle, e.g. while the first instalment is usually payable upon signature and confirmation of commencement of activities and submission of plan of action, subsequent instalments are linked to the submission of an interim report (giving progress of the activities undertaken so far) and an interim certified statement of expenditure (SOE) in the prescribed formats. (See Annexure 3).

h)     For the release of final instalment, the Contractual Partner (CP) must submit a satisfactory FINAL report, both as hard copy and soft copy (Annexure 4), certified FINAL SOE (Annexure 5) and other deliverables, if any, as specified in the APW.

i)       Retroactive conclusion of APW is not permissible.

j)       The execution of work under an APW does not create any employer/employee relationship. The contractual partner is solely responsible for the manner in which the work is carried out.

k)     WHO is not responsible for any loss, accident, damages or injury suffered by any person whatsoever arising during the conduct of activities in relation to the APW. The ownership of the original work (resulting from APW) and copying thereof is vested in WHO, which also reserves the right (a) to revise the work after consultation with the contractual partner; (b) to use the work in a different way from that originally envisaged; or (c) not to publish or use the work at all.

l)       Items generally falling outside the purview of APWs:

-         Capital equipments and consumables (e.g.computers, medical equipments, vehicles, etc.).Instead, these items are covered under supplies & equipment (S&E) for which a separate purchase order (PO) will be raised. Consumables too are normally not covered by an APW. However, requests for minor consumables, which are critically essential for the completion of the work, can be provided.

-         Institutional service charges/administrative overheads and remunerations to Principal Investigators are not to be included in the proposal as these are not payable as per WHO rules.

Responsibilities of Contractual Partner

a)      On receipt of the APW, the Contractual Partner (CP) should satisfy himself/herself that the conditions for the release of different instalments are acceptable.

b)      CP should sign all three copies of the APW and return the original STICKERED version and one copy to WCO along with an explicit written request for the release of the first instalment. The third copy of the APW must be retained by the CP for his/her own records.

c)      CP must quote the Sticker No., which serves as the unique identification number for the APW, in all future correspondences.

d)      The contractual partner (CP) must ensure that the payee's name and bank account details in whose name the cheques/drafts are to be prepared are correctly reflected. The request for release of funds in an individual's name is not allowed.

e)      Funds in local currency will be released only upon receipt of ORIGINAL SIGNED APW.

f)       The contract should start only after the Contractual Partner has signed the contract.

g)      Contractual Partner must ensure compliance with the respective condition while requesting the release of any instalment.

h)      Expenditure should be incurred according to the approved budget for the activity(ies). Justification for variations of more than 10% under any budget head must be incorporated in the SOE.

i)       In case CP is not able to undertake the APW activity, WHO should be informed immediately so that the funds set aside for this activity could be utilized for other priority activities. The funds released, if any, should also be refunded to WHO.

j)       The start date and end date of the APW must be strictly adhered to and the CP should make all efforts to complete the activity/project within the period specified in the APW. The start date of activity is when the CP signs the contract.

k)      If the activity cannot be completed within the stipulated dates for reasons beyond the control of the CP, a request for extension of end date, justifying the extension, should be placed with WCO. WCO will then consider the request, and if approved, will prepare an addendum extending the duration. Subsequent instalments will be released only upon receipt of the addendum duly signed by the CP.

l)       For the release of final instalment, the CP must submit satisfactory FINAL report, certified FINAL SOE and other deliverables, if any, as specified in the APW, immediately after completion of the activity.

m)    In case the activity has been completed with the funds already released and no further instalments are required, the final SOE and final technical report should be submitted immediately along with the unspent balance, if any, to WHO. Cheques/drafts should be drawn in favour of "WHO" payable at New Delhi.

n)      For any alteration in terms originally agreed upon under the APW, an addendum has to be made which must be signed by both the parties to the agreement and be made a part of the original APW document.

o)      Unspent balance of one activity must not be used for any other activity and should be refunded to WHO.

p)      Supporting financial documents must be retained by the Contractual Partner for a period of five years after the end of the activity and be available for inspection by WHO.

q)      Relevant extracts of Contractual Partner's audited financial statements, expense vouchers, bank statements, etc. must also be made available to WHO upon request.

r)      Due recognition or acknowledgment must be accorded for WHO's support, as appropriate, during the course of the activity and on the final reports/documents. An example is: 'In collaboration with WHO Country Office for India, New Delhi'.

 

 

      

 

| | | | | |